City Holds One & Six Year Street Plan Public Hearing

A public hearing was opened for the One and Six Year Street Plan during the March 2 meeting of the Minden City Council. Jeff Palick from Olsson Associates presented the One and Six Year Street Plan.

The One Year Plan is the same as the previous year with the removal of projects on the downtown square which were completed during the Downtown Revitalization Project. The remaining projects on the plan include the paving and drainage projects that were recently completed. The projects remained on the One Year Plan because they were completed during this calendar year.

Two new projects were added to the Six Year Plan. The first is a paving project on S. Colorado between St. Clair and Hastings. The street is currently gravel and will be converted to a concrete street with curb and gutter. The project is estimated at $172,000.
see March 11 courier for full story