Hospital Trustees Discuss Renovation

Dan Janes of Beckenhauer Construction was on hand to give the Kearney County Health Services Board of Trustees an update of the ongoing expansion project at their meeting on Wednesday, April 25.
“More brick is up,” he said, “and they should be off the west side by the end of the week.”
Overall, brick work was estimated to be done in two to three weeks. Janes is anxious to get them done so that preparations can be completed for paving the parking lot to the south.
In the three coming weeks, Janes said they planned to pour ramps and replace half of the emergency entrance. Additionally, the hospital needed to have its oxygen tank refilled during the process.